PROGRESS AND ACHIEVEMENT OF 2ND PHASE NLUP UNDER FISHERIES DEPARTMENT.

Click here to DOWNLOAD

I.  2ND PHASE NLUP

A.  FINANCIAL PROGRESS

1. Fund receipt for 2nd Phase (2012-2013)

(1) Financial target per family (Beneficiary)  =   Rs  1.00 lakh

(2) Fund receipt under ACA (300+980)    =  Rs  890.00 lakh

(3) Fund receipt under CSS  =   NIL

(4) Balance from 1st phase  =  Rs.  0.5 lakhs

    TOTAL  =  Rs  890.50 lakh

2. Target amount issued in each instalment per Beneficiary:

(1) 1st Instalment  =  Rs  0.50 lakh

(2) 2nd Instalment  =  Rs  0.20 lakh

(3) 3rd instalment  =  Rs  0.30 lakh

  TOTAL  =  Rs  1.00 lakh

Note: 1st installment amounting to Rs.50,000/- each has already been given to the beneficiaries as per revised calendar of work.

3. Total requirement of fund for implementation of 2nd phase NLUP:

(1)

1st instalment Rs.50,000 each for 1131  beneficairies

=

Rs.565.50 lakh

(2)

2nd instalment Rs.20,000 each for 1131 beneficairies

=

Rs.226.20 lakh

(3)

3rd instalment Rs.30,000 each for 1131 beneficiaries

=

Rs.339.30 lakh

TOTAL:-

=

Rs.1131.00 lakh

Note: Rs.0.82 lakhs has been given to 1 additional beneficiary due to change of trade from Industry (i.e. Agarbati) to Fishery. 

4.  Additional amount requirement for

  implementation of 2nd phase NLUP    =  Rs.241.32 lakh

B.  PHYSICAL PROGRESS

1.  (1) Target of beneficiary    =  1200 Families

(2) Achievement of beneficiaries  =  1131 Families.

2. District wise target and list of beneficiaries for 2nd phase NLUP:-

Sl. No.

Name of District

Proposed Target for 2nd Phase of NLUP

No of Beneficiaries for 2nd  Phase of NLUP

1

Aizawl

100

139

2

Lunglei

150

151

3

Saiha

50

43

4

Kolasib

250

157

5

Mamit

250

206

6

Lawngtlai

200

145

7

Serchhip

100

100

8

Champhai

100

190


TOTAL

1200

1131

3.  For 2nd phase beneficiaries, Training on Fish culture practices, construction of pond, management of pond etc. has already been conducted in all 8(eight) district.

4.  The calendar of work was revised as desired by the Apex Board meeting and Implementing Board of NLUP for successful implementation of 2nd phase NLUP.

II.  PROPOSE IMPLEMENTATION FOR 3RD & 4TH PHASE NLUP.

A.  Development Component:- The Department proposed to implement

3rd & 4th phase NLUP as per present calendar of work.

B.  Infrastructure Component:- The Department proposed to implement construction of hatchery, nursery and rearing pond in private sector through PPP basis for production of fish seeds and to attain self sufficiency of fish seeds.

III.  Problem face by the Department on Implementation of NLUP  programme.

a)  Due to shortage of technical staff in the Department, it is very difficult to take spot verification and monitoring properly.

b)  Since the NLUP Vehicles have been allotted to only 3(three) Districts, the remaining 5 (five) districts face difficulty in spot verification and monitoring etc for proper implementation of NLUP.

c)  Some of the selected beneficiaries does not have enough land for creation of 0.5 ha. of new pond and this creates problem for successful implementation of NLUP.

d)  As change of trades is one of the problems for the Department achievement and progress report cannot be constant.